
Project Type: Rope Access VESDA Fire Detection Pipe Installation
Location: Bristol
Scope of Work: Installation and routing of VESDA fire detection pipework at roof level
Team Deployment: Rapid mobilisation of a two-person IRATA-certified rope access team
Access Method: IRATA-compliant rope access and rigging techniques
Overview:
Think Access Ltd. was appointed to deliver urgent rope access support for the installation of VESDA fire detection pipework within a cold storage facility in Avonmouth, Bristol. With commissioning dates approaching and the programme already delayed, immediate mobilisation was essential. This was required to maintain the overall project timeline and ensure the system was brought online as scheduled. Notably, Fire Detection Pipe Installation at the facility required special rope access techniques.
The cold store roof was limited to a maximum load bearing capacity of 2 kN/m². Due to this restriction, conventional access methods such as scaffolding or MEWPs were not feasible. The imposed loads would have exceeded the structural allowance. Rope access provided the only practical and compliant solution. This enabled the works to be completed safely and efficiently. In addition, the roof structure was not overloaded.
Rapid Mobilisation and Planning:
Following initial contact, Think Access attended site within 48 hours to assess access limitations and confirm the full scope of installation requirements. Additionally, Fire Detection Pipe Installation required careful planning. This was essential to meet all site safety and compliance requirements.
Behind the scenes, our Contracts Manager (IRATA Level 3) worked alongside our Health & Safety team to produce detailed, site-specific RAMS (Risk Assessments and Method Statements). These were issued and approved within an accelerated timeframe to meet programme demands. In parallel, our stores team prepared all required rope access equipment, tools and associated lifting accessories. They ensured full certification compliance, inspection checks were up to date, and everything was ready for immediate mobilisation.
A two-person IRATA-certified rope access team was mobilised to site on Friday evening. This allowed works to commence first thing Saturday morning. The onsite team prepared a task-specific rescue plan, which was submitted through our Get Konnected portal and received immediate approval from our IRATA Technical Authority at head office. This ensured full compliance and oversight prior to works progressing.
The team operated throughout the weekend under the approved rescue arrangements. They completed the installation on Monday in line with the client’s commissioning schedule. As a result, there was no programme delay.




Scope and Challenges:
Key project challenges included:
Roof load limitations: With a maximum load capacity of 2 kN/m², the roof could not support scaffolding, MEWPs, or other conventional access systems. Rope access provided a safe alternative without imposing additional structural load.
Time-critical programme: The installation needed to be completed immediately to allow commissioning to proceed as scheduled. In fact, Fire Detection Pipe Installation had to be finished under strict programme deadlines.
Working at height in construction conditions: The cold store was still under construction, requiring strict adherence to health and safety protocols and a robust rescue plan in case of incidents.
Coordination and readiness: Rapid mobilisation required the seamless coordination of Health & Safety, stores and operational teams to ensure equipment, documentation and personnel were ready for deployment on short notice.
Execution:
The rope access team guided and installed the VESDA pipework across roof-level areas, using precise techniques to ensure correct routing and alignment. All fixings were installed to specification. In addition, the team’s deployment included:
- Implementation of a site-specific rescue plan
- Continuous monitoring of structural integrity and load limits
- Safe handling of materials and tools at height
- Full compliance with approved RAMS
Working through the weekend, the team maintained high efficiency and completed all works on schedule. In summary, Fire Detection Pipe Installation was performed expertly using rope access.
Results and Impact:
The project was delivered safely, efficiently, and within the compressed timeframe, enabling commissioning to start without delay.
Key outcomes:
- Complete VESDA pipework installation at roof level
- Rapid recovery of project schedule, from site visit on Wednesday to completion Monday
- Successful deployment and execution of site-specific rescue plan
- All equipment and operations fully compliant with approved RAMS
- Rope access allowed safe installation despite roof load limitations of 2 kN/m²
This rapid response ensured the project could proceed with commissioning as planned. It demonstrated Think Access Ltd.’s capability to mobilise quickly and deliver specialist installation solutions under challenging conditions.
Conclusion:
This project highlights Think Access Ltd.’s capability in rapid mobilisation, high-level rope access operations and controlled project delivery under programme pressure. Through direct coordination between our Contracts Manager (IRATA Level 3), Health & Safety department, IRATA Technical Authority and operational team, all approvals, rescue planning and compliance requirements were closed out without delay.
Need urgent rope access support for critical installations?
Think Access Ltd delivers fast mobilisation, safe access solutions, and reliable project delivery across the UK.









